Burke County Airport (BXG) Terminal Building Waynesboro, GA
Status
Bidding Closed
Bid Date | 2/4/25 4:00pm |
Company
Location
Burke County Airport Waynesboro, GA
(Look at the project manual T-100 for minimum specs required. This is a design-build project so if the T-100 does not give you enough info, make a few assumptions and price something low/middle of the road. )
(Please see addendum # 1 and #2 )
The Airport Terminal Building Development Project includes site improvements and building construction to
develop a new 2,495-square-foot terminal building at the Burke County Airport, adjacent to the existing parking
lot and aircraft apron, as shown in the construction documents.
The scope of construction work includes airport terminal area site grading, site erosion control, asphalt pavement
(access drive and parking lot), concrete curb and sidewalk, stormwater conveyance, site utility work
(power/electric services, communications, water line and septic system), fencing, grassing, and landscaping.
The scope further includes the design-build construction of a 2,495-square-foot terminal building as detailed in
the attached building criteria specifications/requirements for all trades and services to produce a fully functioning
building facility.
A further summary of the Airport Terminal Building Development – site work includes contractor furnishing all
labor, materials, equipment, and services to provide the following as detailed in the construction documents:
1. Establishment of a secure staging area
2. Installation of required erosion control measures
3. Preparation of the site for terminal building construction to include
• survey/construction staking,
• minor clearing and stripping of topsoil for reuse,
• site grading for proposed condition including hauling surplus material to the airport stockpile
within the east airport limits,
• subgrade preparation for building foundation including fine grading and stabilization,
• subgrade preparation for asphalt paving and curbing,
• stormwater pipe and inlet installation,
• miscellaneous utility installation (power services, communications services, water line
connection at the existing wellhead, and installation of a new septic system),
4. Building pad preparation, including subgrade utility preparations and foundation/footing preparation
5. Asphalt paving of the drive lane and parking lot with temporary and permanent/final pavement marking
complete upon final curing of asphalt
6. Installation of ancillary site elements including airport terminal signage, LED parking lot lighting and 30-
foot flag pole with LED lighting
7. Security fencing and access gates, including one (1) motorized/controlled access gate (24-foot), one (1)
manual swing gate (20-foot) and two (2) manual personnel swing gates (3-foot) with KABA Simplex (or
approved equal) style CypherLocks
7. Landscaping, grassing, and removing erosion control measures
8. Final site cleanup and restoration
A further summary of the Airport Terminal Building Development – building facility work includes the contractor
furnishing all labor, materials, equipment, and services to provide the following as detailed in the construction
documents:
1. Construction of a terminal building that meets or exceeds applicable National, State, and Local
construction codes and ordinances
2. Construction of a terminal building that provides:
a. Passenger Lounge
b. Pilot Lounge
c. Pilot Briefing Area
d. Administration
e. Conference Room
f. Snack Bar with Sitting Area
g. Vending Area
h. Restrooms (24/7 with Airside Access)(Men’s, Women’s and separate ADA)
i. Storage
j. Mechanical
k. Circulation
3. All architectural, structural, mechanical, electrical, and plumbing components as detailed or outlined by the design
intent of the construction documents
4. All required County permitting – permit fees will be waived by Burke County
5. Commissioning and Completed Certificate of Occupancy