SCOPE OF WORK
DIV TRADE GENERAL DESCRIPTION
Site Acreage: 1.07 AC
Building SF: 6,549 SF
Structural Type: Masonry/ Wood Framed
Brief Project Description: Scrap and new build. Demo of existing building NOT containing asbestos and demoing parking lot and ground up EOC building with a basement. Pit features a sump pump system and foundation waterproofing. Site includes a modular retaining wall with fall protection fencing.

2. Site Construction
2-b Demolition (Interior or Exterior) Yes- Building demo and parking lot demo/ Please include traffic control at entrance demo
2-c Erosion Control Yes
2-d Sitework, Grading Yes- Please include excavation, and backfill & compaction of the pit, refer to the architecturals (-8' -2" top of pit slab per A203)/Please include site demo/ If you are including site concrete scope, please include everything on site/ Please include backfilling curbs and the basement CIP walls, include compaction/Please include any traffic control needed at entrance
2-f Site Utilities (Storm, Water, Sewer) Yes- Please include Sump Pump and Manhole structure on west side of pit, please include connection of discharge pipe to the storm system per A-102 details/ Please include nyoplast basin per A-102, plumber will furnish and install the sump pump/ Please include roof drains and connections to the storm system per grading plan/ Please include domestic and irrigation BFP's and meters
2-j Striping & Site Signage Yes
2-k Asphalt paving Yes- Heavy Duty and Light duty per C-302
2-m Landscaping Yes
2-n Irrigation Yes- Please include sleeves
2-o Retaining Wall Yes- Please include modular retaining wall, also include fall protection fencing and sleeves for fencing
2-p Fencing Yes- Fall protection fencing for the new retaining wall.
2-q NPDES Monitoring Yes
2-r Surveying Yes
2-s Construction Material Testing Yes

3. Concrete
3-a Soil Treatment Yes
3-b Concrete Material Yes, 3000/4000 PSI / Estimated CY:  450-500 CY
3-c Concrete Labor Yes- Please include Basement walls/ Please include stone, rebar, pumps, and equipment/ Please break out site scope from building scope
3-d Concrete Turnkey Proposals Yes- Please include Basement walls/ Please include stone, rebar, pumps, and equipment/ Please break out site scope from building scope
3-e Concrete Pumping Yes
3-f Stone / Aggregate Yes, #57 Stone / Estimated tons: 350-400 TN
3-g Rebar / Wire Mesh Yes- Rebar for building concrete/ Site concrete/ Dumpster enclosure/ All Masonry
3-k Cast-in-Place Wall (CIP) Yes- Pit walls

4. Masonry
4-a Brick Material Yes- Quik Brick Structural Half Highs
4-b Block Material Yes- Quik Brick Structural Half Highs/ 8" Reg/ 8" SF/ 8" Bond
4-c Masonry Accessories Yes
4-d Masonry Labor Yes- Please include building and dumpster
4-e Masonry Turnkey Yes- Please include building and dumpster
4-k Precast (Sills, Water Table, Caps) Yes

5. Metals
5-c Building Steel Turnkey Yes- Please include building, site, and dumpster

6. Carpentry
6-d Countertops Yes
6-i Wood Truss Material Yes
6-j Wood Truss Install Yes
6-k Lumber Material - Structural Wood Yes
6-l Lumber Install (Bldg Framing) Yes- Please include building and dumpster roof
6-m Bolt Package Yes

7. Thermal and Moisture Protection
7-b Roofing - Metal Roofing Yes- Please include building and dumpster
7-h Batt Insulation Yes
7-k Caulking Yes- Please include 4" drain pipe at the footings/ Please include foundation waterproofing per A-102 details/ Please include joint sealants/ Please include weather barrier/ Please include masonry repellent
7-l Moisture Protection Yes- Please include 4" drain pipe at the footings/ Please include foundation waterproofing per A-102 details/ Please include joint sealants/ Please include weather barrier/ Please include masonry repellent

8. Doors and Windows
8-a Doors, Frames, Hardware Yes
8-b Doors, Frames, Hardware Install Yes
8-c Garage/Roll-up Doors Yes
8-e Storefront & Glass Yes

9. Finishes
9-b Drywall & Metal Studs Yes; please include wood blocking in your quote
9-e Flooring (Ceramic or Quarry Tile) Yes
9-f Flooring (Polished, Stained, Epoxy, Sealed) Yes- Please include Rexthane with Shark Grip
9-k Painting (Interior & Exterior) Yes

10. Specialties
10-a Bathroom Accessories Yes
10-b Fire Extinguishers Yes
10-d Awnings Yes- CP Dothan- Jeff- (334) 798- 0330/ (1) 12' wide canopy
10-s Bollards, Covers & Sleeves Yes - Ideal shield bollard sleeve

15. Mechanical
15-a Plumbing Yes- Please include furnishing and installing the sump pump/ Please include Furnishing and install the oil water sep.
15-e HVAC Turnkey Yes- Please include wall and ceiling EF's

16. Electrical
16-d Electrical Turnkey Yes- Please include all the site electrical, please refer to the utility plan C-501 and Site Electrical E104

This is just a reminder that there are 2 buildings for this project, thank you!