SCOPE OF WORK
DIV TRADE GENERAL DESCRIPTION
Site Acreage: 2.85 AC
Building SF: 5,537 SF
Structural Type: Steel & Metal Stud
Brief Project Description:  Pad Ready Site. Concrete footing spoils will need to be hauled off. Asphalt and Concrete Paving on site.  Structural steel building with metal stud infill.  Exterior finishes are Hardie, Stucco, Stone & ATAS.

2. Site Construction
2-c Erosion Control Yes
2-d Sitework, Grading Yes - Please Include Canopy Footer Spoils
2-f Site Utilities (Storm, Water, Sewer) Yes- Please include the Planter Drains (D3.0)/ Please include connection to the Fuel Canopy Drains/ Please include the Grease Trap/Please Include Water Line to Dumpster
2-j Striping & Site Signage Yes
2-k Asphalt paving Yes - 1.25"/2"/10" (See C6-01)
2-m Landscaping Yes - Please Include Planter Boxes
2-n Irrigation Yes
2-p Fencing Yes - 4' Vinyl Coated Chain Link at Pond
2-q NPDES Monitoring Yes
2-r Surveying Yes

3. Concrete
3-a Soil Treatment Yes
3-b Concrete Material Yes, 3000/4000 PSI / Estimated CY:  350
3-c Concrete Labor Yes
3-d Concrete Turnkey Proposals Yes - Please Include Stamped and Colored Concrete per A11.0/Please Include Canopy Footers per CS2.0
3-e Concrete Pumping Yes
3-f Stone / Aggregate Yes, #57 Stone / Estimated tons: 500
3-g Rebar / Wire Mesh Yes

4. Masonry
4-b Block Material Yes- 8" Reg/ 8" BB
4-c Masonry Accessories Yes
4-d Masonry Labor Yes
4-e Masonry Turnkey Yes - Please Include Stone on Canopy Columns and Sign
4-j Stone Turnkey Yes - Please Include Stone on Canopy Columns and Sign
4-k Precast (Sills, Water Table, Caps) Yes- Boral Stone (Taupe CSV-1375)/Italian Cast Stone (White)

5. Metals
5-a Building Steel Material Yes - Ladder and Cage

6. Carpentry
6-a FRP Material Yes - Acrovyn Sheets at Specified Walls and Doors (A0.5 for Details)
6-b FRP Install Yes
6-c Cabinetry Yes - Install (See EQ-1.0)
6-h Kitchen Equipment (Install Only) Yes - Install (See EQ-1.0)

7. Thermal and Moisture Protection
7-a Roofing - TPO, Duralast, Flat Roof Yes - Single Ply Membrane (R-40)
7-b Roofing - Metal Roofing Yes - ATAS Metal Roofing (A4.0 for Detail)/Please include Ice & Water Shield
7-e ACM Panels Yes - ATAS at Soffit of Overhang
7-f Stucco or EFIS Yes
7-g Hardie Board Yes- Please include Accent trim & Azek
7-h Batt Insulation Yes
7-k Caulking Yes

8. Doors and Windows
8-a Doors, Frames, Hardware Yes
8-b Doors, Frames, Hardware Install Yes
8-e Storefront & Glass Yes - Kawneer Trifab IR501 and 450/Please include Spandrel Glass
8-g Window Film Yes- Opaque Vinyl Film

9. Finishes
9-a Acoustical Yes - Install
9-b Drywall & Metal Studs Yes; please include wood blocking in your quote/Please include Rigid Insulation where Shown/Please include Stainless Steel Wall Panels/Please include Cement Board & Durock/Please include Plywood Decking at Restroom Ceilings and Tower
9-c Metal Trusses Yes - At Tower
9-e Flooring (Ceramic or Quarry Tile) Yes
9-f Flooring (Polished, Stained, Epoxy, Sealed) Yes - Terrazzo
9-j Flooring (Speciality) Yes - Ultra Entry Mats (Mary Crane (781)573-0285))/Anti Fatigue Surface (Ecore International)
9-k Painting (Interior & Exterior) Yes

10. Specialties
10-a Bathroom Accessories Yes
10-b Fire Extinguishers Yes
10-e Shutters Yes - Prefinished Aluminum Baha Shutter
10-f Blinds Yes - Roller Shades at all Glazing Below 11'0"

15. Mechanical
15-a Plumbing Yes
15-e HVAC Turnkey Yes
15-g Mechanical Testing & Balance Yes

16. Electrical
16-d Electrical Turnkey Yes - Please Stub up to Fueling Canoy for Petroleum Contractor to do the Remaining/Please Include Conduit and Wire for Canopy Lighting
16-e Fire Alarm Yes
16-h Audio/Visual Yes - Run Conduit
16-i Camera/Security Yes - Run Conduit